A Solar Plant appointed Logan Bruce to deliver the complete fencing installation package for the plant — a 30.07 MWp solar energy facility located in the heart of Fife, Scotland. The scope encompasses the design, supply, and installation of a permanent perimeter deer fence and a temporary Health & Safety (H&S) fence across four land plots with a combined perimeter exceeding 5,958 metres and a total site area of 386,270 m².
The fencing works form a critical enabling package within the wider solar development, required to secure the site perimeter ahead of the main solar installation programme whilst simultaneously protecting construction personnel from high-voltage infrastructure present within the plant boundary. Works are ongoing and are scheduled for completion in July 2026.
Logan Bruce is constructing a permanent deer fencing installation designed to a 30-year service life across all four plots. Key construction details include:
All materials and methodology comply with British Standard BS 1722 — Fences. The site’s classification as a C3 corrosive ambient environment drove the selection of fully galvanised steelwork throughout.
Running to approximately 2,900 metres, the temporary H&S fencing system is installed within the plant boundary to segregate multiple high-voltage electrical lines during the construction phase. The system:
Logan Bruce implemented a controlled plant movement strategy, routing machinery along designated access corridors to limit ground disturbance on agricultural land during the wet March 2026 conditions. Temporary trackway was deployed at key crossing points to protect the ground surface and maintain safe access for excavator-mounted post drivers throughout the installation phase.
The permanent deer fence was specified and constructed to BS 1722, with HT13/190/15 high-tensile galvanised mesh selected to meet both the structural demands of the terrain and the C3 corrosion environment. No cantilever, overhang, or barbed wire elements were incorporated, in keeping with the client’s specification and environmental best practice. Post and strainer positions were surveyed and set out to accommodate gradient changes, ensuring consistent mesh tension across the full 5,958-metre perimeter.
Mammal gates (20 × 20 cm) were integrated into the fence line at 150-metre intervals, allowing smaller native mammals to move freely through the site boundary. This approach satisfied the projects biodiversity net gain commitments without any compromise to the primary deer-exclusion function, and was coordinated with the project ecologist prior to installation.
The temporary H&S fencing system was designed and installed in strict compliance with applicable Health & Safety regulations, establishing clearly defined exclusion zones around all live electrical infrastructure within the plant. The safety management framework governed the interface between Logan Bruce’s fencing operatives and other contractors working in proximity to energised equipment, with exclusion zones maintained and monitored throughout the construction programme.
Works across the four plots were sequenced to prioritise the largest perimeter areas, enabling the solar installation contractor to take early possession of secured zones. Regular programme reviews ensured resource levels were adjusted as ground conditions evolved and construction activity on adjacent packages progressed.
The fencing installation commenced in March 2026 and are progressing on schedule for completion in July 2026. Interim outcomes to date include:
Upon completion, the project will have delivered over 5,958 metres of permanent perimeter deer fencing alongside 2,900 metres of temporary safety fencing across four plots, all within challenging Scottish weather conditions and a demanding construction programme. The project demonstrates Logan Bruce’s capability to deliver technically complex civil scopes on large-scale renewable energy developments to programme.